Here is a quick update on where we are on our construction project.

Week 45

What we’ve done in week 45?

  • The structural framework is now 90% complete, giving a clear visual of the center’s impressive design. The foundation is stronger than ever, and we’re getting closer to a fully enclosed building.

  • A major milestone—roofing materials have arrived, and installation is in progress! This brings us one step closer to sealing the building and beginning interior work.

  • The heating, ventilation, and air conditioning (HVAC) system installation has begun, ensuring that the facility will be comfortable year-round once completed.

  • Significant progress has been made on electrical wiring, with major sections now powered up. This allows for lighting, security systems, and essential building functions to start taking shape.

  • The interior walls for office spaces, training rooms, and classrooms are being framed, making the vision of an educational and entrepreneurial hub come to life.

  • We hosted on-site tours for key stakeholders, donors, and community members, giving them a first-hand look at the progress and impact this center will bring to Woodlawn.

Every brick laid, every wire connected, and every milestone reached is made possible by you—our incredible supporters.

Your donations aren’t just contributions; they’re investments in a future where lives are transformed, opportunities are created, and communities thrive. This project is more than just a building—it’s a beacon of hope, a hub for economic empowerment, and a place where dreams turn into reality.

With your continued generosity, we can keep the momentum going and bring this vision to life. Every dollar fuels progress, ensuring that we can complete this center and provide life-changing resources for those who need them most. Together, we are Helping Others Obtain Destiny.